Construction Information

Construction Information

ConstructionInformation_Header

Construction Schedule (May 8, 2019)

Here is an overview of the construction work taking place in April, 2019.

Zone

Work Being Done

Potential Impact

A

May 6-10

Building demolition wrapping up.

Clean-up of site and underpinning removal. Intermittent noise and dust.

B

May 13-24

Crews are preparing to excavate for the new culvert by installing a de-watering system to remove groundwater from the future excavation.

Vertical wells will be drilled along the path of culvert and pumps and pipes installed to remove excess water. Noise, dust from well-drilling equipment.

News

Public Asked Not to Interfere with Construction Signs

May 10, 2019
The Department of Public Works reminds residents that construction signs or barrels should not be moved or interfered…

Culvert Construction Proceeding On Track

May 10, 2019
Recent reports of Construction delay are unfounded Construction on the Brock St. Culvert project is entering a new…

Centennial Drive Closed to Through Traffic May 8th

May 7, 2019
Construction work near the Uxbridge Brook on Centennial Dr. will close the road to through-traffic and pedestrians on…

The Road to the Culvert

Project-Timeline

Design Phase:

  • The design phase of the project began prior to January of 2018 and wrapped up in May 2018.

Contract Tendering:

  • The tender for the Construction contract opened in mid-March and closed June 25th, 2018. Contractors were pre-qualified. Three firms bid on the construction contract. It was awarded to Brennan Paving and Construction from Markham, Ont.

Construction Phase:

  • Construction will begin mid-September 2018 and will continue well into 2019. Specific schedules for each part of the project will be posted as they become available.
ProjectPlanningTimeline_Culvert

For Businesses

Do you have a business within the culvert construction zone? We have information specifically for you.