Construction Information

Construction Information

Updated_ConstructionInformation_Header

Construction Schedule and Stages (Nov., 2019)

The Brock St. Culvert Replacement project is removing the existing culvert that runs under Downtown Uxbridge and replacing it with a pair of twinned culverts. The existing culvert, sections of which are 120 years old, is in a state of failure and does not have enough capacity to prevent significant flooding in a major storm event. Here is an overview of the construction work taking place in November, 2019.

Zone

Work Being Done

Potential Impact

A

Retaining Walls

A concrete retaining wall is being installed along the path of the culvert. This work is almost complete North of Brock St.

  • Interlocking concrete pillars are drilled/poured along the path of the excavation. The pillars will act as a retaining wall to keep the sides of the excavation from collapsing.

Ongoing through November.

Noise

B

On-site water removal and decontamination
  • Water removed from the aquifer below the construction site is being cleaned as it passes through a series of filters before being released back into the Uxbridge Brook
Noise from generator operating the pump.

C

Excavation and installation of culvert sections.
  • Excavators will begin removing soil. Culvert sections will arrive on-site and be installed from the North side towards Brock St.
Sidewalk access limited in front of the buildings for several weeks, on the South side.Potential for intermittent noise and dust.

Construction Schedule and Stages (Nov., 2019)

The Brock St. Culvert Replacement project is removing the existing culvert that runs under Downtown Uxbridge and replacing it with a pair of twinned culverts. The existing culvert, sections of which are 120 years old, is in a state of failure and does not have enough capacity to prevent significant flooding in a major storm event. Here is an overview of the construction work taking place in November, 2019.

Zone

Work Being Done

Potential Impact

A

Retaining Walls

A concrete retaining wall is being installed along the path of the culvert. This work is almost complete North of Brock St.

  • Interlocking concrete pillars are drilled/poured along the path of the excavation. The pillars will act as a retaining wall to keep the sides of the excavation from collapsing.

Ongoing through November.

Noise

B

On-site water removal and decontamination
  • Water removed from the aquifer below the construction site is being cleaned as it passes through a series of filters before being released back into the Uxbridge Brook
Noise from generator operating the pump.

C

Excavation and installation of culvert sections.
  • Excavators will begin removing soil. Culvert sections will arrive on-site and be installed from the North side towards Brock St.
Sidewalk access limited in front of the buildings for several weeks, on the South side.Potential for intermittent noise and dust.

Construction Schedule and Stages (July, 2019)

The Brock St. Culvert Replacement project is removing the existing culvert that runs under Downtown Uxbridge and replacing it with a pair of twinned culverts. The existing culvert, sections of which are 120 years old, is in a state of failure and does not have enough capacity to prevent significant flooding in a major storm event. Here is an overview of the construction work taking place in the summer.

Zone

Work Being Done

Potential Impact

A

Ongoing

Crews are installing a de-watering system to remove groundwater from the future excavation.

  • Vertical wells will be drilled along the path of culvert and pumps and pipes installed to remove excess water.
Noise, dust from well-drilling equipment.

B

Through July

Installation of Secant Walls along the path of the excavation.

  • Interlocking concrete pillars are drilled/poured along the path of the excavation. The pillars will act as a retaining wall to keep the sides of the excavation from collapsing.
Noise, increased volume of trucks to site.

Construction Schedule (May 8, 2019)

Here is an overview of the construction work taking place in April, 2019.

Zone

Work Being Done

Potential Impact

A

May 6-10

Building demolition wrapping up.

Clean-up of site and underpinning removal. Intermittent noise and dust.

B

May 13-24

Crews are preparing to excavate for the new culvert by installing a de-watering system to remove groundwater from the future excavation.

Vertical wells will be drilled along the path of culvert and pumps and pipes installed to remove excess water. Noise, dust from well-drilling equipment.

News

Brock St. Closed Until End of September 2020

May 25, 2020
A portion of Brock St. W. will be closed to through-traffic, from Tuesday, May 25th through to the…

Culvert Construction Update

July 8, 2019
Culvert Construction Has Been Delayed on the North side of Brock St. W because of low-level soil and…

Public Asked Not to Interfere with Construction Signs

May 10, 2019
The Department of Public Works reminds residents that construction signs or barrels should not be moved or interfered…

The Road to the Culvert

Project-Timeline

Design Phase:

  • The design phase of the project began prior to January of 2018 and wrapped up in May 2018.

Contract Tendering:

  • The tender for the Construction contract opened in mid-March and closed June 25th, 2018. Contractors were pre-qualified. Three firms bid on the construction contract. It was awarded to Brennan Paving and Construction from Markham, Ont.

Construction Phase:

  • Construction will begin mid-September 2018 and will continue well into 2019. Specific schedules for each part of the project will be posted as they become available.
ProjectPlanningTimeline_Culvert

For Businesses

Do you have a business within the culvert construction zone? We have information specifically for you.